Time For An Update - Feb 4th

Last week saw the framers finish up, what wood they didn't use got sent back or burned, or ended up behind my barn.  Front stairs turned out nice, there are two sets on the front porch and one at the rear of the house.  The fireplace installers showed up and installed the fireplace in one day. On the next day, Friday, they installed the fire brick.  We purchased an Isokern fireplace.  It is really interesting, a Danish product also produced in the US.   Made from volcanic ash and formed into building blocks like legos.  Lighter than a true masonry fireplace, about half the cost, but just as nice or nicer.


Adding two dormers on rear of house


 

Building stairs


    Front-side stairs


    Making sure it fits!


    Assembling the fireplace




    Firebox assembled

    All Assembled, pretty good size fireplace, the fire box opening is  44" wide and 41" tall


    Adding the chimney.... made from same material, it is a two part system with the square block you see and an additional flue liner inside.



    We spent a little extra to have the firebrick split and installed in a herringbone pattern.   Really looks good!



    Installing firebrick


    Finished for now, fireplace surround, mantel , all come later in the build



    Porch columns arrived and were installed Friday as well.



    I'll put a white lattice under the porch floor in due time.


    Home for the weekend.  Have granddaughter, Layla's 2 year old birthday party, Super bowl, pack up a bunch of tools, etc.  Back on about Wed. and hopefully the plumber is ready to start his rough-in.

    Monday, January 28, 2013

    4th and 5th Week of January

    Well, this has been another productive couple of weeks as you will see in the photos.  For those interested I am using Google blogger which is a free service and saves me emailing out allot of pictures to all interested.  My framing crew, Joe Rodger's Construction out of Mineola, TX has been super.  I'm also using Cade's Building Supply, also out of Mineola.

    The house is turning out exactly as we pictures and planned for.  I've learned a few things along the way which I will share when appropriate.



      Garage

    Weather holding out thank god!



    There is allot of wood in this house!  I added 1/2 inch of foam to outside stud to act as a thermal break.










    Note my "office& temporary home"  is now dwarfed in the back.
     
    I'm using Louisiana Pacific Smart siding for out exterior lap siding and trim.  I't a wood product with a 50 year warranty.  Pre-primed and much easier to work with than the popular Hardie siding.


    Front side... Still needs some stairs.  The front porch is 632 square feet.

    Doors and windows in


    Two faux dormers going on back.  The one dormer closest is actually a skylight into the kitchen!

    Rear Porch is actually three section.  On right is a walk out from master bedroom.  In the middle is a screened porch with walkout from living room, all connect to the rear kitchen door with a breezeway.




    Find Waldo, I mean Reg :)


     

    Discussing something this past weekend, something important I'm sure!






     Stewart came up with Reg this past weekend and attended a welcoming party with the neighbors. There were three other couples there with kids.  He took this one of Reg and I..


    So do you think it looks like the drawing at the top of this blog??


    Sunday, January 20, 2013

    Continuation of 3rd week of Jan 2013

    Second day of full framing saw all of the first floor walls up as well a garage.  We are framing with 10 foot tall walls, 2x6 exterior wall construction with 24 inches on center studs - this considered "advanced framing" and provides additional insulation.  There will also be 1/2 inch of foam over the house wrap to serve as a thermal barrier to heat/cold through the studs.


    This one wall was framed with 16 in on center studs till the boss caught the mistake.


    Weather turned nice with 50-60 degrees during the days, still chilly at night.



    Rear views







    The little vaulted ceiling you see here in in the master bath.


    The vaulted ceiling here is over the kitchen.  There will be a roof over all of this.


    Here you can see the 1/2 in foam being added



    Regina came up for the weekend and brought grandson Aidan


    Stay tuned, next week will be a big one!